does Dave have enough experience to be a excavation competent person

A person submitted this question to Rosie's free generator. The asker's identity is neither imported nor published.

Rosie's answer

Published by SALUS

To determine if Dave has enough experience to be a competent person for excavation work, you need to assess whether he meets the definition of a "competent person" as defined by OSHA [1]. A competent person is someone who:

  1. Is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees [1].
  2. Has the authorization to take prompt corrective measures to eliminate these hazards [1].

To determine if Dave is a competent person you must evaluate his knowledge and ability to recognize hazards related to the specific excavation site, and his authority to correct those hazards. Some factors to consider include:

  • Soil Type and Stability: Can Dave assess soil conditions and identify potential cave-in hazards? [1]
  • Protective Systems: Does Dave understand the requirements for protective systems like sloping, shoring, and shielding? [2]
  • Underground Utilities: Can Dave identify and locate underground utilities before excavation? [3]
  • Hazardous Atmospheres: Is Dave able to test for and recognize hazardous atmospheres, such as low oxygen levels or flammable gases? [4]
  • Water Hazards: Can Dave recognize and address hazards associated with water accumulation in the excavation? [5]
  • Inspection Procedures: Is Dave capable of performing daily inspections of the excavation, adjacent areas, and protective systems for any evidence of potential hazards? [6]

If Dave can demonstrate these abilities and has the authority to take corrective actions, he can be considered a competent person. If there are any doubts about Dave's competence, it may be necessary to provide him with additional training or supervision.

6 source record(s)

Sources used for this answer

[1] Safety and Health Regulations for Construction (OSHA)

Page 93

Open source document

Source excerpt

## 29 CFR 1926 (OSHA) Support system means a structure such as underpinning, bracing, or shoring, which provides support to an adjacent structure, underground installation, or the sides of an excavation. Tabulated data means tables and charts approved by a registered professional engineer and used to design and construct a protective system. Trench (Trench excavation) means a narrow excavation (in relation to its length) made below the surface of the ground. In general, the depth is greater than the width, but the width of a trench (measured at the bottom) is not greater than 15 feet (4.6 m). If forms or other structures are installed or constructed in an excavation so as to reduce the dimension measured from the forms or structure to the side of the excavation to 15 feet (4.6 m) or less (measured at the bottom of the excavation), the excavation is also considered to be a trench. Trench box. See 'Shield.' ## Trench shield. See 'Shield.' Uprights means the vertical members of a trench shoring system placed in contact with the earth and usually positioned so that individual members do not contact each other. Uprights placed so that individual members are closely spaced, in contact with or interconnected to each other, are often called 'sheeting.' Wales means horizontal members of a shoring system placed parallel to the excavation face whose sides bear against the vertical members of the shoring system or earth. ## §1926.651 Specific excavation requirements. - (a) Surface encumbrances. All surface encumbrances that are located so as to create a hazard to employees shall be removed or supported, as necessary, to safeguard employees. - (b) Underground installations. (1) The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation. - (2) Utility companies or

[2] Safety and Health Regulations for Construction (OSHA)

Page 95

Open source document

Source excerpt

## 29 CFR 1926 (OSHA) - (iii) Adequate precaution shall be taken such as providing ventilation, to prevent employee exposure to an atmosphere containing a concentration of a flammable gas in excess of 20 percent of the lower flammable limit of the gas. - (iv) When controls are used that are intended to reduce the level of atmospheric contaminants to acceptable levels, testing shall be conducted as often as necessary to ensure that the atmosphere remains safe. - (2) Emergency rescue equipment. (i) Emergency rescue equipment, such as breathing apparatus, a safety harness and line, or a basket stretcher, shall be readily available where hazardous atmospheric conditions exist or may reasonably be expected to develop during work in an excavation. This equipment shall be attended when in use. - (ii) Employees entering bell-bottom pier holes, or other similar deep and confined footing excavations, shall wear a harness with a life-line securely attached to it. The lifeline shall be separate from any line used to handle materials, and shall be individually attended at all times while the employee wearing the lifeline is in the excavation. - (h) Protection from hazards associated with water accumulation. (1) Employees shall not work in excavations in which there is accumulated water, or in excavations in which water is accumulating, unless adequate precautions have been taken to protect employees against the hazards posed by water accumulation. The precautions necessary to protect employees adequately vary with each situation, but could include special support or shield systems to protect from cave-ins, water removal to control the level of accumulating water, or use of a safety harness and lifeline. - (2) If water is controlled or prevented from accumulating by the use of water removal equipment, the water removal equipment and operations shall be monitored by a competent person to ensure proper operation. - (3) If excavation work interrupts the natural drainage of surface

[3] Safety and Health Regulations for Construction (OSHA)

Page 94

Open source document

Source excerpt

- (c) Access and egress -(1) Structural ramps. (i) Structural ramps that are used solely by employees as a means of access or egress from excavations shall be designed by a competent person. Structural ramps used for access or egress of equipment shall be designed by a competent person qualified in structural design, and shall be constructed in accordance with the design. - (ii) Ramps and runways constructed of two or more structural members shall have the structural members connected together to prevent displacement. - (iii) Structural members used for ramps and runways shall be of uniform thickness. - (iv) Cleats or other appropriate means used to connect runway structural members shall be attached to the bottom of the runway or shall be attached in a manner to prevent tripping. - (v) Structural ramps used in lieu of steps shall be provided with cleats or other surface treatments on the top surface to prevent slipping. - (2) Means of egress from trench excavations. A stairway, ladder, ramp or other safe means of egress shall be located in trench excavations that are 4 feet (1.22 m) or more in depth so as to require no more than 25 feet (7.62 m) of lateral travel for employees. - (d) Exposure to vehicular traffic. Employees exposed to public vehicular traffic shall be provided with, and shall wear, warning vests or other suitable garments marked with or made of reflectorized or high-visibility material. - (e) Exposure to falling loads. No employee shall be permitted underneath loads handled by lifting or digging equipment. Employees shall be required to stand away from any vehicle being loaded or unloaded to avoid being struck by any spillage or falling materials. Operators may remain in the cabs of vehicles being loaded or unloaded when the vehicles are equipped, in accordance with §1926.601(b)(6), to provide adequate protection for the operator during loading and unloading operations. - (f) Warning system for mobile equipment. When mobile equipment is operated ad

[4] Safety and Health Regulations for Construction (OSHA)

Page 96

Open source document

Source excerpt

- (iv) A registered professional engineer has approved the determination that such excavation work will not pose a hazard to employees. - (3) Sidewalks, pavements, and appurtenant structure shall not be undermined unless a support system or another method of protection is provided to protect employees from the possible collapse of such structures. - (j) Protection of employees from loose rock or soil. (1) Adequate protection shall be provided to protect employees from loose rock or soil that could pose a hazard by falling or rolling from an excavation face. Such protection shall consist of scaling to remove loose material; installation of protective barricades at intervals as necessary on the face to stop and contain falling material; or other means that provide equivalent protection. - (2) Employees shall be protected from excavated or other materials or equipment that could pose a hazard by falling or rolling into excavations. Protection shall be provided by placing and keeping such materials or equipment at least 2 feet (.61 m) from the edge of excavations, or by the use of retaining devices that are sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary. - (k) Inspections. (1) Daily inspections of excavations, the adjacent areas, and protective systems shall be made by a competent person for evidence of a situation that could result in possible cave-ins, indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions. An inspection shall be conducted by the competent person prior to the start of work and as needed throughout the shift. Inspections shall also be made after every rainstorm or other hazard increasing occurrence. These inspections are only required when employee exposure can be reasonably anticipated. - (2) Where the competent person finds evidence of a situation that could result in a possible cave-in, indications of failure of protective sys

[5] Safety and Health Regulations for Construction (OSHA)

Page 92

Open source document

Source excerpt

## 29 CFR 1926 (OSHA) Failure means the breakage, displacement, or permanent deformation of a structural member or connection so as to reduce its structural integrity and its supportive capabilities. Hazardous atmosphere means an atmosphere which by reason of being explosive, flammable, poisonous, corrosive, oxidizing, irritating, oxygen deficient, toxic, or otherwise harmful, may cause death, illness, or injury. Kickout means the accidental release or failure of a cross brace. Protective system means a method of protecting employees from cave-ins, from material that could fall or roll from an excavation face or into an excavation, or from the collapse of adjacent structures. Protective systems include support systems, sloping and benching systems, shield systems, and other systems that provide the necessary protection. Ramp means an inclined walking or working surface that is used to gain access to one point from another, and is constructed from earth or from structural materials such as steel or wood. Registered Professional Engineer means a person who is registered as a professional engineer in the state where the work is to be performed. However, a professional engineer, registered in any state is deemed to be a 'registered professional engineer' within the meaning of this standard when approving designs for 'manufactured protective systems' or 'tabulated data' to be used in interstate commerce. Sheeting means the members of a shoring system that retain the earth in position and in turn are supported by other members of the shoring system. Shield (Shield system) means a structure that is able to withstand the forces imposed on it by a cavein and thereby protect employees within the structure. Shields can be permanent structures or can be designed to be portable and moved along as work progresses. Additionally, shields can be either premanufactured or job-built in accordance with §1926.652 (c)(3) or (c)(4). Shields used in trenches are usually referred to

[6] Safety and Health Regulations for Construction (OSHA)

Page 91

Open source document

Source excerpt

## 29 CFR 1926 (OSHA) ## Subpart P-Excavations AUTHORITY: Sec. 107, Contract Worker Hours and Safety Standards Act (Construction Safety Act) (40 U.S.C. 333); Secs. 4, 6, 8, Occupational Safety and Hea1th Act of 1970 (29 U.S.C. 653, 655, 657); Secretary of Labor's Order No. 12-71 (36 FR 8754), 8-76 (41 FR [redacted postal code]), or 9-83 (48 FR [redacted postal code]), as applicable, and 29 CFR part 1911. SOURCE: 54 FR [redacted postal code], Oct. 31, 1989, unless otherwise noted. ## §1926.650 Scope, application, and definitions applicable to this subpart. (a) Scope and application. This subpart applies to all open excavations made in the earth's surface. Excavations are defined to include trenches. ## (b) Definitions applicable to this subpart. Accepted engineering practices means those requirements which are compatible with standards of practice required by a registered professional engineer. Aluminum Hydraulic Shoring means a pre-engineered shoring system comprised of aluminum hydraulic cylinders (crossbraces) used in conjunction with vertical rails (uprights) or horizontal rails (walers). Such system is designed, specifically to support the sidewalls of an excavation and prevent cave-ins. Bell-bottom pier hole means a type of shaft or footing excavation, the bottom of which is made larger than the cross section above to form a belled shape. Benching (Benching system) means a method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels. Cave-in means the separation of a mass of soil or rock material from the side of an excavation, or the loss of soil from under a trench shield or support system, and its sudden movement into the excavation, either by falling or sliding, in sufficient quantity so that it could entrap, bury, or otherwise injure and immobilize a person. Competent person means one who is capable of

Related Q&A

Keep exploring.

Human questionUS

Write a toolbox talk on Trench collapse

A trench collapse can happen suddenly and with enough force to crush, trap, or suffocate workers. One cubic yard of soil can weigh about 3,000 pounds, and cave-ins are the leading hazard in excavation work. Never allow anyone to enter an unprotected trench, even briefly. [1] [2] [6] Main hazards include cave-ins

Read the thread
Human questionUS

Write a safety checklist for Drop hammer piling rig checklist

A safe pre-start and operating checklist for a drop hammer piling rig should require a documented inspection, confirmation that the rig is stable, verification that the hammer/leads/rigging are in safe condition, and a review of the lift plan, exclusion zones, communications, and emergency arrangements before work

Read the thread
Human questionGeneral

Safety

Toolbox Talk: Pre-Start Safety for Excavators *Date:** [DATE] *Duration:** [DURATION] minutes *Presenter:** [PRESENTER NAME] *Location:** [LOCATION] Objective The objective of this toolbox talk is to ensure that all operators understand the importance of pre-start safety checks and procedures for excavators to prevent

Read the thread
Human questionGeneral

Trench

Safe Work Procedure: Trenching Document Number: [SWP-NUMBER] Revision Date: [DATE] Next Review Date: [NEXT REVIEW DATE] Department: [DEPARTMENT NAME] 1. Scope This Safe Work Procedure (SWP) outlines the safety requirements and procedures for trenching activities to protect workers from cave-ins, falling materials, and

Read the thread
Human questionUS

Excavations

Toolbox Talk: Excavation Safety *Date:** [DATE] *Duration:** [DURATION] minutes *Presenter:** [PRESENTER NAME] *Location:** [LOCATION] Objective The objective of this toolbox talk is to educate participants on the safety measures and best practices for working in and around excavations. By the end of this session

Read the thread
Human questionGeneral

Trenching

Toolbox Talk: Trenching Safety *Date:** [DATE] *Duration:** [DURATION] minutes *Presenter:** [PRESENTER NAME] *Location:** [LOCATION] Objective To educate workers on the hazards associated with trenching and excavation work, and to provide them with the knowledge and procedures necessary to perform these tasks safely

Read the thread
Discussion thread

Add your experience.

Community answers can add practical context. They are moderated, but they are not SALUS-reviewed safety guidance.

New contributions are temporarily closed while the moderation queue is configured.

Community answers(0)

No community answers have been approved yet.

Comments on Rosie's answer(0)

No comments have been approved yet.

Ready to put operational safety to work?

Join 400K users across 150K sites already on SALUS.

No commitment · 30-minute personalized walkthrough