create a Job Hazard Analysis for a electrical contractor doing a start up of a new electrical switchboard

A person submitted this question to Rosie's free generator. The asker's identity is neither imported nor published.

Rosie's answer

Published by SALUS

JHA for Electrical Switchboard Startup and Commissioning ========================================================

Assessment Date: \[DATE]

Assessor: \[ASSESSOR NAME]

Department/Area: \[DEPARTMENT/AREA]

Review Date: \[REVIEW DATE]

1\. Assessment Scope


This Job Hazard Analysis (JHA) covers the initial startup and commissioning of new electrical switchboards by qualified electrical contractors. It includes all tasks from initial inspection to energization and testing. The scope excludes routine maintenance or repair work on existing energized switchboards after the initial commissioning phase.

2\. Risk Assessment Methodology


This risk assessment follows a qualitative approach using a 5x5 risk matrix to determine risk ratings. The methodology includes: 1\) Hazard Identification, 2\) Risk Assessment (Likelihood x Severity), 3\) Control Measure Implementation (following the hierarchy of controls), and 4\) Residual Risk Assessment.

3\. Risk Matrix Reference


The following matrix is used to evaluate risk levels based on likelihood and severity:

Likelihood

| Rare | Unlikely | Possible | Likely | Almost Certain | | Severity | Catastrophic | Low | Low | Medium | Medium | High | | Major | Low | Medium | Medium | High | Extreme | | Moderate | Medium | Medium | High | Extreme | Extreme | | Minor | Medium | High | High | Extreme | Extreme | | Negligible | High | High | Extreme | Extreme | Extreme |

4\. Hazard Identification and Risk Evaluation


1\. Electrical Shock

Potential Consequences: Cardiac arrest, burns, muscle contractions, and death.

Affected Persons: Electricians, technicians, and any personnel in the vicinity.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
PossibleCatastrophicHigh
Control Measures
  • De-energize and lockout/tagout the switchboard before starting work.
  • Use insulated tools and PPE (gloves, safety glasses, and arc flash suit).
  • Verify the absence of voltage using a calibrated meter before touching any parts.
  • Maintain appropriate clearance from energized parts.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
RareMajorLow

2\. Arc Flash

Potential Consequences: Severe burns, blindness, hearing damage, and potentially fatal injuries.

Affected Persons: Electricians and technicians.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
UnlikelyCatastrophicHigh
Control Measures
  • Conduct an arc flash risk assessment to determine appropriate PPE requirements.
  • Wear appropriate arc-rated clothing and PPE.
  • Use remote switching devices where possible.
  • Ensure proper grounding of equipment.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
RareMajorLow

3\. Explosion

Potential Consequences: Serious burns, shrapnel injuries, structural damage.

Affected Persons: Electricians, technicians, and nearby personnel.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
RareCatastrophicMedium
Control Measures
  • Ensure proper ventilation in the switchboard room.
  • Inspect switchboard for any signs of damage or deterioration before energization.
  • Follow manufacturer's recommendations for startup procedures.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
RareMajorLow

4\. Falls from Height

Potential Consequences: Fractures, head injuries, sprains, and strains.

Affected Persons: Electricians and technicians accessing elevated switchboard components.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
PossibleMajorMedium
Control Measures
  • Use ladders or scaffolding that meet safety standards.
  • Ensure ladders are properly secured and placed on a stable surface.
  • Wear fall protection equipment (harness and lanyard) when working at heights above 6 feet.
  • Maintain three points of contact when climbing ladders.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
UnlikelyModerateLow

5\. Exposure to Hazardous Materials

Potential Consequences: Skin irritation, respiratory problems, chemical burns.

Affected Persons: Electricians and technicians.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
UnlikelyModerateLow
Control Measures
  • Review Safety Data Sheets (SDS) for all chemicals used.
  • Use appropriate PPE (gloves, eye protection, and respiratory protection) when handling chemicals.
  • Ensure adequate ventilation when working with chemicals.
  • Properly store and dispose of hazardous materials.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
RareMinorLow

6\. Confined Space Entry

Potential Consequences: Asphyxiation, exposure to toxic gases, electrocution.

Affected Persons: Electricians and technicians entering switchboard enclosures or rooms.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
RareMajorMedium
Control Measures
  • Evaluate if the space meets the definition of a confined space.
  • Follow confined space entry procedures, including atmospheric testing, ventilation, and standby personnel.
  • Use appropriate PPE, including respiratory protection.
  • Ensure proper training for confined space entry.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
RareModerateLow

7\. Ergonomic Hazards (Strain from Lifting, Awkward Postures)

Potential Consequences: Musculoskeletal disorders (MSDs), back injuries, sprains, and strains.

Affected Persons: Electricians and technicians.

Initial Risk Assessment
LikelihoodSeverityRisk Rating
PossibleModerateMedium
Control Measures
  • Use proper lifting techniques (bend knees, keep back straight).
  • Use mechanical aids (dollies, forklifts) to move heavy equipment.
  • Take frequent breaks and rotate tasks to reduce repetitive motions.
  • Ensure adequate lighting and workspace.
Residual Risk Assessment
LikelihoodSeverityRisk Rating
UnlikelyMinorLow

5\. General Control Measures


  • All electrical work must be performed by qualified and competent electricians.
  • Use properly insulated tools and equipment that are regularly inspected.
  • Ensure proper grounding and bonding of all electrical equipment.

Refer to local electrical codes for grounding requirements.

  • Maintain a safe working distance from energized parts.
  • Implement a lockout/tagout procedure before commencing any work on electrical equipment.

Follow OSHA standard 1910\.147 for lockout/tagout procedures.

6\. Emergency Preparedness


  • In case of electrical shock, immediately disconnect the power source if safe to do so. Call emergency services (911\) and provide first aid/CPR as needed.
  • For arc flash incidents, evacuate the area and ensure medical attention for affected personnel.
  • In the event of a fire, use a Class C fire extinguisher and evacuate the area. [1]

7\. Training Requirements


  • Electrical Safety Training: All electricians and technicians must complete a comprehensive electrical safety training program that covers topics such as: NFPA 70E, arc flash awareness, lockout/tagout procedures, and safe work practices.
  • First Aid/CPR Training: Personnel should be trained in first aid and CPR, including how to respond to electrical shock.
  • Hazardous Materials Handling: Training on the safe handling, storage, and disposal of hazardous materials, including proper PPE and emergency procedures.
  • Fall Protection Training: Workers who may be exposed to fall hazards must receive training on the proper use of fall protection equipment, including harness inspection, lifeline attachment, and rescue procedures.
  • Confined Space Entry Training: Workers who may enter confined spaces must be trained on confined space entry procedures, including atmospheric testing, ventilation, and rescue procedures.

8\. Monitoring and Review


Review Frequency: Annually, or after any incident or significant change in equipment or procedures.

Monitoring TypeFrequencyResponsible PartyDescription
Regular InspectionWeeklySite SupervisorInspect all electrical tools and equipment for damage. Ensure all safety devices are in place and functioning correctly.
Performance IndicatorMonthlySafety ManagerTrack the number of near misses and incidents related to electrical work.
AuditAnnuallySafety DepartmentConduct a comprehensive audit of electrical safety procedures and practices.
Review of JHAAnnually or after any incidentSafety Manager and Site SupervisorReview the JHA to ensure it remains relevant and effective.

9\. Special Circumstances


  • Work during inclement weather (rain, snow) increases the risk of electrical shock. Postpone work if weather conditions are unsafe.
  • Night work reduces visibility and increases the risk of trips and falls. Ensure adequate lighting is provided.
  • Lone work increases the response time in case of an emergency. Implement a buddy system or regular check-in procedures.
  • Ensure proper ventilation in confined spaces to prevent accumulation of hazardous gases. [1]

Approval and Sign-off


This risk assessment has been reviewed and approved by:

Assessor: _________________________ Date: __________

Manager/Supervisor: _________________________ Date: __________

Safety Representative: _________________________ Date: __________

This risk assessment must be reviewed annually, or after any incident or significant change in equipment or procedures. or when significant changes occur.

Safety powered by SALUS

1 source record(s)

Sources used for this answer

[1] Occupational Health and Safety Regulations, 2020 (Sask. Reg. 10/2020)

Page 232

Open source document

Source excerpt

232 Electrical panels 30‑12 An employer or contractor shall ensure that every electrical panel is: (a) approved for the intended use and location of the electrical panel; (b) protected from physical or mechanical damage; (c) readily accessible; and (d) fitted with an approved cover that has an approved filler in any unused opening. 31 Dec 2020 c S-15.1 Reg 10 s30-12. High voltage switchgear and transformers 30‑13(1) An employer or contractor shall ensure that a place where electrical switchgear or transformers operating at high voltage are housed is: (a) guarded; (b) kept free of extraneous material; and (c) adequately ventilated. (2) If high voltage switchgear or transformers are housed, an employer or contractor shall post a warning sign that: (a) indicates the highest voltage in use; and (b) states that access is restricted to authorized persons only. 31 Dec 2020 c S-15.1 Reg 10 s30-13. Fire extinguishers 30‑14 An employer or contractor shall ensure that a fire extinguisher approved for Class C fires is readily available to workers working on or near energized high voltage electrical equipment. 31 Dec 2020 c S-15.1 Reg 10 s30-14. Grounding of equipment before work begins 30‑15 Before any work, other than work to which subsection 30-16(4) applies, begins on an electrical conductor or electrical equipment and during the progress of that work, an employer or contractor shall ensure that: (a) the electrical conductor or electrical equipment is isolated, locked out and connected to ground; or (b) other effective procedures are taken to ensure the safety of the workers. 31 Dec 2020 c S-15.1 Reg 10 s30-15. Proximity to exposed energized high voltage electrical conductors 30‑16(1) In this section: “applied science technologist” means an applied science technologist who is registered pursuant to The Saskatchewan Applied Science Technologists and Technicians Act and whose registration has not been suspended or…

Related Q&A

Keep exploring.

Human questionUS

line break safe work procedure

Safe Work Procedure: Line Breaking Operations ============================================= Document Number: \[SWP-NUMBER] Revision Date: \[DATE] Next Review Date: \[NEXT REVIEW DATE] Department: \[DEPARTMENT NAME] 1\. Scope This safe work procedure (SWP) outlines the necessary steps and safety precautions for safely

Read the thread
Human questionGeneral

Write a risk assessment for House refurbishment

For house refurbishment and renovation works, the risk assessment should be task-specific, site-specific, and reviewed as the job changes. Under UK good practice and CDM principles, start by identifying hazards, who may be harmed, existing controls, and additional controls required, then communicate the findings to all

Read the thread
Human questionUS

Write a pre-task plan for Daily safety briefing

A compliant pre-task plan and daily safety briefing should be completed before work starts and updated whenever conditions, scope, personnel, or controls change. The process should be site-specific and should use a documented job hazard analysis (JHA/JSA) to break the work into steps, identify hazards for each step

Read the thread
Human questionUS

Write a risk assessment for FAHU replacement

A suitable safe system of work for replacing a Fresh Air Handling Unit (FAHU) should begin with a task-specific risk assessment, coordination with the client/site operator, and a permit-to-work package covering isolation, lifting, work at height, electrical work, hot work if applicable, and any confined-space elements.

Read the thread
Discussion thread

Add your experience.

Community answers can add practical context. They are moderated, but they are not SALUS-reviewed safety guidance.

New contributions are temporarily closed while the moderation queue is configured.

Community answers(0)

No community answers have been approved yet.

Comments on Rosie's answer(0)

No comments have been approved yet.