Here is a High-Rise Construction Safety Checklist, designed to be used daily, and to be retained for the duration of the project [1].

High-Rise Construction Safety Checklist

I. General Safety Precautions

  • [ ] Is the work site kept clean and free from slip and trip hazards? [2]
    • Corrective Actions:
  • [ ] Is lighting sufficient for safe work? [2]
    • Corrective Actions:
  • [ ] Are light sources protected from damage? [2]
    • Corrective Actions:
  • [ ] Is emergency lighting available and functional? [2]
    • Corrective Actions:
  • [ ] Are hoses and piping restrained to prevent injury? [3]
    • Corrective Actions:
  • [ ] Is equipment and material secured to prevent dislodgement? [3]
    • Corrective Actions:
  • [ ] Are workers protected from falling objects with overhead barriers? [4]
    • Corrective Actions:
  • [ ] Are areas where workers may be struck by falling objects clearly marked? [5]
    • Corrective Actions:

II. Fall Protection

  • [ ] Is a fall protection plan readily available? [6]
    • Corrective Actions:
  • [ ] Have workers been trained in the fall protection plan and safe use of fall protection systems? [6]
    • Corrective Actions:
  • [ ] If control zones are used, are they at least 2 meters wide and clearly marked? [6]
    • Corrective Actions:
  • [ ] Are workers within control zones using travel restraint systems? [6]
    • Corrective Actions:
  • [ ] Do anchor points have the required load capacity (3.5 kN for travel restraint, 22.2 kN for fall arrest)? 3, 6
    • Corrective Actions:
  • [ ] Are anchor points installed and used according to manufacturer's specifications? 3, 6
    • Corrective Actions:
  • [ ] Are permanent anchor points marked for travel restraint only? 3, 6
    • Corrective Actions:
  • [ ] Are temporary anchor points removed upon completion of the work? [6]
    • Corrective Actions:
  • [ ] Are stairways with 5 or more treads equipped with handrails? [5]
    • Corrective Actions:
  • [ ] Are open sides of stairways equipped with handrails and intermediate rails? [5]
    • Corrective Actions:
  • [ ] Are openings or holes in floors, roofs, or work surfaces covered or guarded? [7]
    • Corrective Actions:
  • [ ] Do covers have a warning sign or permanent marking indicating the hazard? [7]
    • Corrective Actions:

III. Scaffold Safety

  • [ ] Are scaffolds erected, used, and dismantled under the supervision of a qualified person? [8]
    • Corrective Actions:
  • [ ] Are scaffolds inspected before each use, and are damaged components tagged and removed? [8]
    • Corrective Actions:
  • [ ] Are workers using fall arrest equipment when working on adjustable suspended scaffolds or near unguarded edges? [9]
    • Corrective Actions:
  • [ ] Are adjustable suspended platforms operated away from live power lines, or have proper precautions been taken? 13, 14
    • Corrective Actions:
  • [ ] Is debris prevented from accumulating on scaffold platforms? [9]
    • Corrective Actions:
  • [ ] Are wire ropes and attachments used as specified by the hoisting machine manufacturer? 13, 16
    • Corrective Actions:
  • [ ] Are platforms and cages equipped with proper guardrail systems? [10]
    • Corrective Actions:
  • [ ] Are all components securely fastened to prevent them from falling off the platform? [10]
    • Corrective Actions:
  • [ ] Are toeboards provided at edges where materials could fall more than 3 meters from a temporary scaffold or work platform? [7]
    • Corrective Actions:

IV. Cranes and Hoisting

  • [ ] Is the tower crane equipped with an overload device, travel limit device, height limit switch, and trolley travel limit devices? [11]
    • Corrective Actions:
  • [ ] Are the crane's limit devices adjusted and set according to the manufacturer's specifications? [11]
    • Corrective Actions:
  • [ ] Does the crane operator ensure the safe movement of the crane and its load at all times? [11]
    • Corrective Actions:
  • [ ] Is the mast plumb, and are the limit devices operational at the beginning of each work shift? [11]
    • Corrective Actions:
  • [ ] Are test weights used on tower cranes of a known and recorded weight? [11]
    • Corrective Actions:
  • [ ] Is the lifting attachment on a test weight made of mild steel and of sufficient strength? [11]
    • Corrective Actions:

V. Electrical Safety

  • [ ] Are power cords and connections grounded and protected with circuit breakers? [10]
    • Corrective Actions:
  • [ ] Are power cords of the proper size and long enough for the job? [10]
    • Corrective Actions:
  • [ ] Are power cords tied off at the suspended scaffold to prevent them from falling? [10]
    • Corrective Actions:
  • [ ] Are power cords protected at sharp edges? [10]
    • Corrective Actions:

VI. Other

  • [ ] Are erection drawings and procedures for skeleton structures prepared and certified by a professional engineer? [3]
    • Corrective Actions:
  • [ ] Do erection drawings show the sequence of erection and ensure structural stability during assembly? [3]
    • Corrective Actions:
  • [ ] Is a competent worker coordinating the erection of skeleton structures until permanently stabilized? [3]
    • Corrective Actions:
  • [ ] Are supplies and roofing materials stored at least 2 meters from the roof edge on residential buildings? [2]
    • Corrective Actions:
  • [ ] Is the weight of supplies and roofing materials uniformly distributed? [2]
    • Corrective Actions:

Inspected by: __________________________

Date: __________________________

Supervisor Signature: __________________________

11 source record(s)

Sources used for this answer

[1] Occupational Health and Safety Code

Page 123

Open source document

Source excerpt

## Part 12 General Safety Precautions ## Housekeeping 185 An employer must ensure that a work site is kept clean and free from materials or equipment that could cause workers to slip or trip. ## Lighting 186 (1) An employer must ensure that lighting at a work site is sufficient to enable work to be done safely. 186 (2) An employer must ensure that a light source above a working or walking surface is protected against damage. - 186 (3) An employer must ensure that there is emergency lighting at a work site if workers are in danger if the normal lighting system fails. - 186 (4) Emergency lighting must generate enough light so that workers can - (a) leave the work site safely, - (b) start the necessary emergency shut-down procedures, and - (c) restore normal lighting. ## Pallets and storage racks 187 (1) An employer must ensure that pallets used to transport or store materials or containers are loaded, moved, stacked, arranged and stored in a manner that does not create a danger to workers. - 187 (2) An employer must ensure that racks used to store materials or equipment - (a) are designed, constructed and maintained to support the load placed on them, and - (b) are placed on firm foundations that can support the load. - 187 (3) A worker must report any damage to a storage rack to an employer as quickly as practicable. - 187 (4) The employer and the workers at a work site must take all reasonable steps to prevent storage racks from being damaged to the extent that their integrity as structures is compromised. ## Placement of roofing materials - 187.1 (1) An employer must ensure that supplies and roofing materials stored on the roof of a residential building under construction are located not less than 2 metres from a roof edge. - 187.1 (2) An employer must ensure that the weight of supplies and roofing materials referred to in subsection (1) is uniformly distributed.

[2] Spider by Brand Safway: Swing Stage Operator’s Manual

Page 5

Open source document

Source excerpt

- protected by a safety lifebelt attached to a lifeline. The lifeline shall be securely attached to substantial members of the structure (not scaffold), or to securely rigged lines, which will safely suspend the worker in case of a fall. - 11. Two-point suspension scaffolds shall be securely lashed of the building or structure to prevent them from swaying. Window cleaners' anchors shall not be used for this purpose. - 10. Where acid solutions are used, fiber ropes are not permitted unless acid-proof. ## I. Single-point adjustable suspension scaffolds. - 8. The hoisting machines, cables, and equipment shall be regularly serviced and inspected after each installation and every 30 days thereafter. - 9. The units may be combined to form a two-point suspension scaffold. Such scaffold shall comply with paragraph (g) of this section. - 10. The supporting cable shall be straight for it's entire length, and the operator shall not sway the basket and fix the cable to any intermediate points to change his original path of travel. - 11. Equipment shall be maintained and used in accordance with the manufacturers' instructions, - 12. Suspension methods shall conform to applicable provisions of paragraph (g) and (h) of this section. ## Code of safe practices for suspended powered scaffolds It shall be the responsibility of all employers and users to read and comply with the following common-sense guidelines, which are designed to promote safety in the erection and use of suspended powered scaffolds. These guidelines are not allinclusive, nor do they supplant or replace other additional safety and precautionary measures to cover usual and unusual conditions. If these guidelines conflict in anyway with state, local, or federal statute or governmental regulation, said state statute or regulation shall supersede these guidelines, and it shall be the responsibility of each employer and user to comply therewith and also to be knowledgeable and understand all state, local or fed…

[3] Occupational Health and Safety Regulations, 2020 (Sask. Reg. 10/2020)

Page 70

Open source document

Source excerpt

## S-15.1 REG 10 ## OCCUPATIONAL HEALTH AND SAFETY, 2020 - (3) The employer or contractor shall ensure that a copy of the fall protection plan is readily available before work begins at a worksite if a risk of falling exists. - (4) The employer or contractor shall ensure that a worker is trained in the fall protection plan and the safe use of the fall protection system before allowing the worker to work in an area where a fall protection system must be used. 31 Dec 2020 c S-15.1 Reg 10 s9-3. ## Control zone - 9-4 (1) An employer or contractor shall ensure that a control zone: - (a) is only used if a worker can fall from a level surface in a work area; and - (b) is not less than 2 metres wide when measured from the unguarded edge. - (2) When crossing a control zone mentioned in subsection (1), a worker: - (a) subject to subsection (4), is not required to use a fall protection system, other than the control zone, to enter or leave the work area; and - (b) shall follow the most direct route to get to or from the unguarded edge. - (3) An employer or contractor shall ensure that a control zone is clearly marked with an effective raised warning line or other equally effective method if a worker is working more than 2 metres from an unguarded edge. - (4) An employer or contractor shall ensure that a worker who has to work within a control zone uses: - (a) a travel restraint system; or - (b) a means that is as equally effective as a travel restraint system and that prevents the worker from getting to the unguarded edge. 31 Dec 2020 c S-15.1 Reg 10 s9-4. ## Anchor Points and Anchor Plates - 9-5 (1) If a worker uses a personal fall arrest system or a travel restraint system, an employer, contractor or owner shall ensure that an anchor point or anchor plate that meets the requirements of this section is used as part of that system. - (2) An employer, contractor or owner shall ensure that a temporary anchor point used in a travel restraint system: - (a) has an ultimate …

[4] Occupational Health and Safety Code

Page 82

Open source document

Source excerpt

## Limit devices 101 (1) An employer must ensure that a tower crane is equipped with - (a) an overload device consisting of a hoist overload switch that automatically restricts the weight of the load, - (b) a travel limit device consisting of a moment overload switch that automatically restricts the radius within which the load can travel, - (c) a height limit switch that prevents the load from being overwound, and - (d) trolley travel limit devices consisting of a 'trolley in' limit switch and a 'trolley out' limit switch that prevent the trolley from running to the end of its track and falling off. 101 (2) An employer must ensure that the devices described in subsection (1) are adjusted and set in accordance with the manufacturer's specifications and have their limit switches sealed. ## Operation 102 An operator of a tower crane must - (a) ensure the safe movement of the crane and its load at all times, - (b) verify at the beginning of each work shift that the mast is plumb, and - (c) verify at least once in each 24-hour period that the limit devices described in section 101 are operational. ## Changing components 103 (1) An employer must ensure that the major structural, mechanical and electrical components of a tower crane are not interchanged with those of other tower cranes unless - (a) the components are from the same make or model of tower crane, - (b) the components are approved by the manufacturer as suitable for their intended application, or - (c) the components are certified by a professional engineer as suitable for their intended application. 103 (2) An employer must ensure that if an operator's cab is attached to the boom of a tower crane, the design of the cab, its position, method of attachment and any structural changes, including changes to the counterweight, capacity and operation of the crane, are in accordance with the manufacturer's specifications or are certified by a professional engineer. ## Test weights 104 (1) An employer mus…

[5] Occupational Health and Safety Regulations, 2020 (Sask. Reg. 10/2020)

Page 74

Open source document

Source excerpt

S-15.1 REG 10 ## OCCUPATIONAL HEALTH AND SAFETY, 2020 ## Toeboards - 9-12 (1) An employer, contractor or owner shall provide toeboards at the edge of: - (a) a permanent floor, platform, mezzanine, walkway, ramp, runway or other surface from which it is possible for materials to fall more than 1.2 metres; - (b) a temporary scaffold or work platform from which it is possible for materials to fall more than 3 metres; and - (c) a pit for a flywheel or pulley. - (2) Subsection (1) does not apply to a loading or unloading area if the employer, contractor or owner has taken other precautions to ensure that materials will not fall from the floor or other horizontal surface. - (3) If a toeboard is required by these regulations, an employer, contractor or owner shall ensure that the toeboard extends from the floor or other horizontal surface to a height of not less than: - (a) 125 millimetres from the floor or surface; or - (b) 100 millimetres from the floor or surface, in the case of a toeboard that was installed before March 13, 1986. 31 Dec 2020 c S-15.1 Reg 10 s9-12. ## Openings in floors, roofs, etc. - 9-13 (1) An employer, contractor or owner shall ensure that any opening or hole in a floor, roof or other work surface into which a worker could step or fall is: - (a) covered with a securely installed covering that is capable of supporting a load of 360 kilograms per square metre and that is provided with a warning sign or permanent marking clearly indicating the nature of the hazard; or - (b) provided with a guardrail and a toeboard. - (2) If the covering or guardrail and toeboard mentioned in subsection (1) or any part of the guardrail or toeboard is removed for any reason, an employer, contractor or owner shall immediately provide an effective alternative means of protection. 31 Dec 2020 c S-15.1 Reg 10 s9-13. ## Building shafts - 9-14 (1) An employer, contractor or owner shall ensure that a work platform that is an integral part of a slip form used…

[6] Occupational Health and Safety Regulations, 2020 (Sask. Reg. 10/2020)

Page 71

Open source document

Source excerpt

- (3) An employer, contractor or owner shall ensure that a permanent anchor point used in a travel restraint system associated with any new construction project on or after the date this section comes into force: - (a) has an ultimate load capacity of at least 8.75 kilonewtons (2 000 pounds-force) per worker attached in any direction in which the load may be applied; - (b) is installed and used according to the manufacturer's specifications; and - (c) is permanently marked as being for travel restraint only. - (4) In the case of a personal fall arrest system, an employer, contractor, owner or supplier shall ensure that anchor points to which the personal fall arrest system is attached have an ultimate load capacity of at least 22.2 kilonewtons (5 000 pounds-force) per worker attached in any direction in which the load may be applied. - (5) An employer, contractor, owner or supplier shall ensure that the following types of equipment that are components of fall protection systems, and their installation, conform to the manufacturer's specifications or are certified by a professional engineer: - (a) permanent anchor points; - (b) anchors with multiple attachment points; - (c) permanent horizontal lifeline systems; - (d) support structures for safety nets. 31 Dec 2020 c S-15.1 Reg 10 s9-5. ## Elevated conveyors - 9-6 If an elevated conveyor crosses over a place where a worker may pass or work, an employer, contractor or owner shall ensure that suitable precautions are taken to prevent materials on the conveyor from falling on the worker. 31 Dec 2020 c S-15.1 Reg 10 s9-6. ## Wire mesh - 9-7 If wire mesh is required by these regulations, the wire mesh must: - (a) be made from wire that is at least 1.6 millimetres in diameter; and - (b) have a mesh size that is not greater than 40 millimetres by 40 millimetres. 31 Dec 2020 c S-15.1 Reg 10 s9-7. ## Protection against falling objects 9-8 (1) Subject to section 9-9, if a worker is re…

[7] HIOSH Construction Standards: Occupational Safety and Health (12-8-3)

Page 10

Open source document

Source excerpt

order to prevent workplace injuries, illnesses and fatalities. At minimum, inspections shall be in accordance with this schedule: - (1) Projects employing one (1) to ninety-nine (99) persons, at any single moment in the work day, shall have an employee assigned to make at least one inspection each workday; - (2) Projects employing one hundred (100) to one hundred ninety-nine (199) persons shall have two employees assigned, each to make at least one inspection each work day; and - (3) Projects employing two hundred (200) or more persons shall have one additional designated employee for each three hundred (300) persons above one hundred ninety-nine (199) each to make at least one inspection each workday. Exception: Projects employing less than three (3) persons, need not comply with subsection (c). - (c) Written records of the daily safety and health inspections shall be kept on the project site for review by the director for the duration of the project. Inspection records shall include, at minimum, the following: - (1) The date and start time of the inspection; - (2) The name of the employee conducting the inspection; - (3) The scope (project areas) of the inspection, including the names of all contractors and subcontractors covered by the scope of the inspection; - (4) A brief description of all potential and actual hazards noted during the inspection; - (5) Name and title of the person responsible for correcting the identified hazards noted during the inspection; - (6) Information regarding how the hazard was eliminated, corrected, or abated including the inspector's recommendations for preventing the recurrence of the hazards. - (d) Warning signs shall be posted prohibiting unauthorized persons from operating potentially

[8] SAIA: Code of Safe Practices for Adjustable Suspended Scaffolds

Page 2

Open source document

Source excerpt

<!-- image --> - M. ADJUSTABLE SUSPENDED PLATFORMS MUST NEVER BE OPERATED NEAR LIVE POWER LINES unless proper precautions are taken. Contact the power service provider for advice. - N. ALWAYS UTILIZE FALL ARREST EQUIPMENT when working on adjustable suspended scaffolds or when working near unguarded edges. - O. DO NOT WORK FROM, INSTALL OR MOVE ADJUSTABLE SUSPENDED SCAFFOLDS if you are sick or impaired in any way. - P. DO NOT WORK ON ADJUSTABLE SUSPENDED SCAFFOLDS when under the influence of alcohol or drugs. - Q. DEBRIS SHOULD NOT BE STORED OR ALLOWED TO ACCUMULATE ON A PLATFORM. - R. INDEPENDENT ADJUSTABLE SUSPENDED SCAFFOLDS ARE TO BE POSITIONED SO AS TO AVOID OVERLAPPING OR POSSIBLE INTERFERENCE FROM ANOTHER SCAFFOLD. ## II. GUIDELINES FOR ERECTION AND USE OF ADJUSTABLE SUSPENDED SCAFFOLD SYSTEMS ## A. RIGGING: - 1. UTILIZE FALL PROTECTION EQUIPMENT when rigging near unguarded edges. - 2. SUPPORTING DEVICES must be capable of supporting the hoist-rated load with a safety factor of four. - 3. ALL OVERHEAD RIGGING must be secured from unwanted movement in any direction. - 4. COUNTERWEIGHTS USED WITH OUTRIGGER BEAMS must be of a non-flowable material and must be secured to the beam to prevent accidental displacement. - 5. OUTRIGGER BEAMS THAT DO NOT USE COUNTERWEIGHTS must be installed and secured to the roof structure with bolts or other direct connections. Direct connections shall be evaluated by a competent person. - 6. TIE BACK ALL TRANSPORTABLE RIGGING DEVICES. Tieback shall be equivalent in strength to the suspension ropes. - 7. INSTALL TIEBACKS AT RIGHT ANGLES TO THE FACE OF THE BUILDING and secure them without slack, to a suitable anchor capable of supporting the hoist-rated load with a safety factor of four. - 8. IN THE EVENT THAT TIEBACKS CANNOT BE INSTALLED AT RIGHT ANGLES, two tiebacks at opposing angles must be used to prevent movement. - 9. RIG AND USE HOISTING MACHINES DIRECTLY UNDER THEIR SUSPENSION POINTS to prevent movement or side loading. ##…

[9] Spider by Brand Safway: Swing Stage Operator’s Manual

Page 6

Open source document

Source excerpt

## III. Wire rope and hardware guidelines - 1. Use only wire rope and attachments as specified by the hoisting machine manufacturer. Do not use wire rope that is kinked, birdcaged, corroded, undersized, or damaged in any way. - 2. Be sure that wire rope is long enough to reach the lowest possible landing. - 3. Clean, lubricate &amp;amp; handle wire rope in accordance with wire rope or hoist manufacturer's instructions. - 4. Coil and uncoil wire rope in accordance with the wire rope or hoist manufacturer's instruction in order to avoid kinks or damage. - 5. Use thimbles at all wire rope suspension terminations. - 6. Use J-type clamps or swaged fittings to fasten wire rope. DO NOT USE U-CLAMPS. - 7. Tighten wire rope clamps in accordance with the clamp manufacturer's instructions. - 8. Wire ropes used in traction hoists must have prepared ends in accordance with the manufacturer's recommendation. - 9. INSPECT WIRE ROPE DURING EACH ASCENT AND DESCENT. Do not expose wire rope to fire, undue heat, corrosive atmosphere, chemicals, to passage of electrical currents, or to damage by tools or handling. ## IV. Power supply guidelines - 1. BE SURE YOUR POWER SUPPLY CONFORMS TO HOIST MANUFACTURER'S RECOMMENDATIONS. - 2. GROUND ALL ELECTRICAL POWER SOURCES and POWER CORD CONNECTIONS. Protect with circuit breakers. - 4. Power cord or air hose connections must be restrained to prevent their separation. - 3. Use power cords or air hoses of proper size that are long enough for the job. - 5. Tie off power cords or air hoses at the suspended scaffold to prevent them from falling. - 6. Protect power cords or air hoses at sharp edges. - 7. Remember, air hoist require clean, lubricated air. ## V. Fall-arrest equipment guidelines - 1. Each person on a suspended powered scaffold must be attached to a fall-arrest system at all times. - 2. Each lifeline must be fastened to a separate anchorage. - 3. When wrapping lifelines around structural members, the lines must be protected and a sui…

[10] Occupational Health and Safety Code

Page 124

Open source document

Source excerpt

## Restraining hoses and piping - 188 (1) An employer must ensure that a hose or piping and its connections operating under pressure are restrained if workers could be injured by its movement if it fails or if it is disconnected. - 188 (2) Despite subsection (1), if a hose or piping and its connections operating at a working pressure of 2000 kilopascals or more cannot be restrained, in order to prevent a failure that could injure workers, an employer must ensure that the hose or piping and its connections are designed, installed, used, inspected and maintained - (a) in accordance with the manufacturer's specifications, or - (b) in accordance with specifications certified by a professional engineer. - 188 (3) Subsection (1) does not apply to properly maintained fire hoses used by competent workers. ## Securing equipment and materials - 189 If a worker may be injured if equipment or material is dislodged, moved, spilled or damaged, both the employer and the worker must take all reasonable steps to ensure the equipment or material is contained, restrained or protected to eliminate the potential danger. ## Skeleton structures - 190 (1) An employer must ensure that the erection drawings and procedures for a project that includes connecting the structural parts of a skeleton structure are prepared and certified by a professional engineer. - 190 (2) The erection drawings and procedures referred to in subsection (1) must - (a) show the sequence in which the structure is to be erected, - (b) show the horizontal and vertical placement of base structures and footings, and - (c) ensure that the structure is stable during assembly. - 190 (3) If the erection procedures referred to in subsection (1) must be changed because of site conditions or unanticipated loads on the skeleton structure, the employer must ensure that the changed, additional or alternative procedures are prepared and certified by a professional engineer before they are implemented. - 190 (4) An employer mus…

[11] Occupational Health and Safety Regulations, 2020 (Sask. Reg. 10/2020)

Page 72

Open source document

Source excerpt

S-15.1 REG 10 ## OCCUPATIONAL HEALTH AND SAFETY, 2020 - (2) An employer, contractor or owner shall ensure that every area where a worker could be struck by a falling object is clearly marked by barriers, notices, warning lights or other warning devices. 31 Dec 2020 c S-15.1 Reg 10 s9-8. ## Protection from objects falling from scaffolds, etc. - 9-9 (1) If a suspended scaffold, suspended powered scaffold or load-carrying unit is suspended from or attached to a structure, an employer, contractor or owner shall ensure that wire mesh, or other material equally effective to prevent objects from falling from the working surface, is installed from the working surface to a height of at least 900 millimetres on all sides except the side adjacent to the structure. - (2) An employer, contractor or owner shall ensure that wire mesh is installed from the working surface of a platform to a height of 2 metres on all sides of: - (a) a tower hoist as defined in section 13-1; - (b) a building shaft hoist; and - (c) a hoist cage in an excavated shaft. - (3) If it is necessary to hoist or lower materials that are of such a nature that the sides of a cantilever hoist platform or skip cannot be equipped as required by subsection (1), an employer, contractor or owner shall provide another equally effective means for the protection of workers against falling materials. - (4) If it is necessary for workers to pass through a safeguard required by this section, an employer, contractor or owner shall install a gate that is equally effective to prevent objects from falling from the working surface and shall ensure that the gate is kept closed except when the gate is in use. 31 Dec 2020 c S-15.1 Reg 10 s9-9. ## Handrails - 9-10 (1) An employer, contractor or owner shall ensure that a stairway with 5 or more treads: - (a) is equipped with a handrail that: - (i) extends the entire length of the stairway; - (ii) is adequately secured to the structure; - (iii) is installed on …

Related Q&A

Keep exploring.

Human questionGeneral

Write a toolbox talk on railway

A railway safety toolbox talk should begin with the rule that no one goes on or near the line without an authorized safe system of work, a task briefing, and a clear understanding of hazards, limits, and emergency arrangements. Key rail work hazards include moving trains and on-track plant, electrical hazards from

Read the thread
Human questionGeneral

Heat stress and ladder safety

Toolbox Talk: Heat Stress and Ladder Safety *Date:** [DATE] *Duration:** [DURATION] minutes *Presenter:** [PRESENTER NAME] *Location:** [LOCATION] Objective To educate workers on the combined hazards of heat stress and ladder use, enabling them to recognize risks, implement control measures, and follow safe work

Read the thread
Human questionGeneral

Safety works procedures

Safe Work Procedure: General Safety Work Procedures Document Number: [SWP-NUMBER] Revision Date: [DATE] Next Review Date: [NEXT REVIEW DATE] Department: [DEPARTMENT NAME] 1. Scope This Safe Work Procedure (SWP) outlines the general safety practices and procedures to be followed by all employees and contractors to

Read the thread
Human questionGeneral

home chimney inspection

Residential Chimney Inspection Safety ===================================== *Assessment Date:** \[DATE] *Assessor:** \[ASSESSOR NAME] *Department/Area:** \[DEPARTMENT/AREA] *Review Date:** \[REVIEW DATE] 1\. Assessment Scope This risk assessment covers the inspection of residential chimneys to identify and mitigate

Read the thread
Human questionGeneral

Safe Guarding Work Areas in the Elevator Trade

Toolbox Talk: Safe Guarding Work Areas in the Elevator Trade *Date:** [DATE] *Duration:** [DURATION] minutes *Presenter:** [PRESENTER NAME] *Location:** [LOCATION] Objective To ensure all work areas in the elevator trade are safely guarded to prevent falls, falling objects, and other hazards, protecting both workers

Read the thread
Human questionGeneral

Confined space safe work procedure

Confined Space Entry ==================== Document Number: \[SWP-NUMBER] Revision Date: \[DATE] Next Review Date: \[NEXT REVIEW DATE] Department: \[DEPARTMENT NAME] 1\. Scope This safe work procedure outlines the requirements for safe confined space entry, including hazard assessment, atmospheric testing, ventilation

Read the thread
Discussion thread

Add your experience.

Community answers can add practical context. They are moderated, but they are not SALUS-reviewed safety guidance.

New contributions are temporarily closed while the moderation queue is configured.

Community answers(0)

No community answers have been approved yet.

Comments on Rosie's answer(0)

No comments have been approved yet.

Ready to put operational safety to work?

Join 400K users across 150K sites already on SALUS.

No commitment · 30-minute personalized walkthrough